Track Laying Complete, Next Phase Underway on Foynes Freight Line

The reintroduction of freight services on the Limerick to Foynes rail line is one step closer as the laying of the new track is now complete.

The project team, along with construction partners Sisk, have completed the removal of all original line infrastructure, followed by a complete renewal and relaying of 42km of track, sleepers and track bed.

Other key elements undertaken to date by this €151.5 million project include:

  • The removal, restoration and reinstatement of the River Maigue and River Deel bridges
  • Construction of a new 46m span bridge to replace Robertstown Viaduct
  • Upgrading and reinstatement of 13 public road level crossings
  • Renewal of user worked level crossings
  • Boundary fencing works as required along the length of the line

With the line expected to enter operation in 2026, the next phase of works now begins including:

  • Installation of specialist signalling & telecoms infrastructure to enable trains to operate 
  • Refurbishment of Foynes Station building
  • Installation and testing of CCTV at the 13 public road level crossings, a significant safety improvement over previous crossing infrastructure

More information can be found on the project website. 

This article supplied by Irish Rail, Full-Trading Members of IIFA.